Projects
Railway Signalling & Telecommunication (S&T) works executed across Eastern & adjacent zones — interlocking, communication networks, cabling, surveys, installation & commissioning.
Bardhaman–Katwa Section Communication Upgrade
- 24F OFC backbone & 6F access
- Quad cable laying – 52 km with jointing & termination
- EB & TP integration; way-side equipment installation
- As-built documentation & training
- Cutover achieved without traffic block
- 95% link uptime within first 7 days of monitoring
Electronic Interlocking (EI) & Outdoor Gear Works – Sealdah Yard
- EI field wiring & outdoor gears (point machines, signals, track circuits)
- Location boxes fabrication & installation
- Cable termination, testing & commissioning
- Commissioned during night blocks as per safety protocols
- All acceptance tests cleared on first attempt
Capacity Augmentation – Initial Field Survey for 3rd Line
- Route walkouts & site feasibility with GPS referencing
- Preliminary BOQ, WBS & schedule
- Risk register and access planning (ROW, utilities)
- Optimized alignment proposals handed to client
- Stakeholder sign-offs underway
Block Instrument & TP/E1 Link Standardization – Howrah Division
- Block instruments refurbishment & interface standardization
- TP/E1 link testing, alignment & documentation
- Staff orientation & handover
- Reduced fault incidence by 37% over 90 days
- Unified documentation repository delivered
Signalling Cable Renewal – Level Crossings & IBS
- Trenching, HDPE ducting & cable laying for LC gates & IBS
- Jointing, termination & insulation testing
- Earthing & surge protection checks
- Zero NCRs during inspection
- Final test reports submitted within 48 hours of completion
Wayside Communication Assets – Preventive Maintenance
- Periodic inspection & PM of wayside S&T communication assets
- Spare provisioning & fault rectification SLA
- Monthly health reports
- Uptime above 99.2% YTD
- MTTR under 4 hours on average